PROJECT PASSPORT
Lanai Island
Official project no. 2498 · Al Hebiah Fourth
OFFICIAL COMPLETION
48.08%
Latest Mashrooi observation
OFFICIAL STATUS
Active
AREA
Al Hebiah Fourth
LAST EVIDENCE
7/29/2026
OFFICIAL RECORD
Project details
- Registered developer
- MAJID AL FUTTAIM TILAL AL GHAF PHASE A L.L.C
- Master developer
- MAJID AL FUTTAIM EMIRATI COMMUNITIES OPERATION L.L.C
- Area
- Al Hebiah Fourth
- Registration date
- 2023-04-30
- Listed completion date
- 2026-09-30
- Map coordinate
- View this project on the map →
OFFICIAL EVIDENCE
Official inspection photos
Mashrooi photos shown in their supplied resolution.
Source provenance
Official public registry retrieved on 7/28/2026, 3:30:52 PM · Artifact ffee59d637b1… · 3039 dataset rows. Official Mashrooi details retrieved on 7/29/2026, 6:42:15 AM.
Official Mashrooi inspection history
Dates and completion percentages are factual source observations. The latest available official photographs are shown above.
- 2022-11-030.13%Inspection 4526005034 official photo records
- 2023-07-170.15%Inspection 5240228223 official photo records
- 2024-05-010.55%Inspection 6140833412 official photo records
- 2024-12-185.12%Inspection 7088539424 official photo records
- 2025-01-208.01%Inspection 7118262666 official photo records
- 2025-01-2013.61%Inspection 7559972926 official photo records
- 2025-07-1719.4%Inspection 7951699375 official photo records
- 2025-10-2028.61%Inspection 8329542179 official photo records
- 2026-02-1145.64%Inspection 89296463512 official photo records
- 2026-04-0248.08%Inspection 9145708515 official photo records