OFFICIAL COMPLETION
14.75%
Latest Mashrooi observation
OFFICIAL STATUS
Active
AREA
Wadi Al Safa 7
LAST EVIDENCE
7/29/2026
OFFICIAL RECORD
Project details
- Registered developer
- DHRE 2 BTS L.L.C
- Master developer
- DHRE 2 BTS L.L.C
- Area
- Wadi Al Safa 7
- Registration date
- 2024-09-10
- Listed completion date
- —
- Map coordinate
- View this project on the map →
OFFICIAL EVIDENCE
Official inspection photos
Mashrooi photos shown in their supplied resolution.
Source provenance
Official public registry retrieved on 7/28/2026, 3:30:52 PM · Artifact ffee59d637b1… · 3039 dataset rows. Official Mashrooi details retrieved on 7/29/2026, 9:30:03 AM.
Official Mashrooi inspection history
Dates and completion percentages are factual source observations. The latest available official photographs are shown above.
- 2024-03-270%Inspection 6022051804 official photo records
- 2024-11-250.2%Inspection 6941627485 official photo records
- 2025-04-070.25%Inspection 7485942763 official photo records
- 2025-10-030.34%Inspection 8261407584 official photo records
- 2025-11-111.65%Inspection 84463184011 official photo records
- 2026-02-239.07%Inspection 89848816716 official photo records
- 2026-05-1414.75%Inspection 9324533049 official photo records