PROJECT PASSPORT
High Best Tower
Official project no. 3493 · Wadi Al Safa 3
OFFICIAL COMPLETION
90.64%
Latest Mashrooi observation
OFFICIAL STATUS
Active
AREA
Wadi Al Safa 3
LAST EVIDENCE
7/29/2026
OFFICIAL RECORD
Project details
- Registered developer
- TRUE FUTURE REAL ESTATE DEVELOPMENT L.L.C
- Master developer
- MEYDAN GROUP (L.L.C)
- Area
- Wadi Al Safa 3
- Registration date
- 2024-11-01
- Listed completion date
- 2026-11-01
- Map coordinate
- View this project on the map →
OFFICIAL EVIDENCE
Latest official inspection photos
Mashrooi photos shown in their supplied resolution.
Source provenance
Official public registry retrieved on 7/28/2026, 3:30:52 PM · Artifact ffee59d637b1… · 3039 dataset rows. Official Mashrooi details retrieved on 7/29/2026, 1:07:57 PM.
Official Mashrooi inspection history
Dates and completion percentages are factual source observations. The latest available official photographs are shown above.
- 2025-01-2315.75%Inspection 7183309386 official photo records
- 2025-02-1320.1%Inspection 7233159514 official photo records
- 2025-05-2237.66%Inspection 7694912755 official photo records
- 2025-10-1455.05%Inspection 8306599907 official photo records
- 2026-01-2870.22%Inspection 8872578046 official photo records
- 2026-05-1990.64%Inspection 9339434469 official photo records