PROJECT PASSPORT
Gardens 2
Official project no. 2938 · Al Barshaa South Third
ActiveIMAN DEVELOPERS L.L.C
OFFICIAL COMPLETION
68.49%
Latest Mashrooi observation
OFFICIAL STATUS
Active
AREA
Al Barshaa South Third
LAST EVIDENCE
7/29/2026
OFFICIAL RECORD
Project details
- Registered developer
- IMAN DEVELOPERS L.L.C
- Master developer
- LIWAN (L.L.C)
- Area
- Al Barshaa South Third
- Registration date
- 2024-04-20
- Listed completion date
- 2025-12-30
- Map coordinate
- View this project on the map →
OFFICIAL EVIDENCE
Latest official inspection photos
Mashrooi photos shown in their supplied resolution.
Source provenance
Official public registry retrieved on 7/28/2026, 3:30:52 PM · Artifact ffee59d637b1… · 3039 dataset rows. Official Mashrooi details retrieved on 7/29/2026, 9:01:15 AM.
Official Mashrooi inspection history
Dates and completion percentages are factual source observations. The latest available official photographs are shown above.
- 2024-01-260%Inspection 5827118752 official photo records
- 2025-04-0222.55%Inspection 7455319967 official photo records
- 2025-08-0140.37%Inspection 8050357316 official photo records
- 2025-12-1668.49%Inspection 86171068715 official photo records