OFFICIAL COMPLETION
27.64%
Latest Mashrooi observation
OFFICIAL STATUS
Active
AREA
Wadi Al Safa 5
LAST EVIDENCE
7/29/2026
OFFICIAL RECORD
Project details
- Registered developer
- AURORA SPV 1 L.L.C
- Master developer
- DUBAI LAND (L.L.C)
- Area
- Wadi Al Safa 5
- Registration date
- 2024-04-30
- Listed completion date
- 2027-11-28
- Map coordinate
- View this project on the map →
OFFICIAL EVIDENCE
Official inspection photos
Mashrooi photos shown in their supplied resolution.
Source provenance
Official public registry retrieved on 7/28/2026, 3:30:52 PM · Artifact ffee59d637b1… · 3039 dataset rows. Official Mashrooi details retrieved on 7/29/2026, 8:45:42 AM.
Official Mashrooi inspection history
Dates and completion percentages are factual source observations. The latest available official photographs are shown above.
- 2023-12-120%Inspection 5682485783 official photo records
- 2025-01-110.68%Inspection 7130856293 official photo records
- 2025-06-262.47%Inspection 7894275644 official photo records
- 2025-12-047.85%Inspection 85487727510 official photo records
- 2025-12-047.85%Inspection 85495506811 official photo records
- 2026-04-1327.64%Inspection 9200086328 official photo records