PROJECT PASSPORT
Binghatti Pinnacle
Official project no. 3256 · Al Jadaf
ActiveBinghatti Developers FZE
OFFICIAL COMPLETION
97.48%
Latest Mashrooi observation
OFFICIAL STATUS
Active
AREA
Al Jadaf
LAST EVIDENCE
7/29/2026
OFFICIAL RECORD
Project details
- Registered developer
- Binghatti Developers FZE
- Master developer
- DUBAI HEALTHCARE CITY FZ - LLC
- Area
- Al Jadaf
- Registration date
- 2024-09-01
- Listed completion date
- 2025-12-31
- Map coordinate
- View this project on the map →
OFFICIAL EVIDENCE
Latest official inspection photos
Mashrooi photos shown in their supplied resolution.
Source provenance
Official public registry retrieved on 7/28/2026, 3:30:52 PM · Artifact ffee59d637b1… · 3039 dataset rows. Official Mashrooi details retrieved on 7/29/2026, 11:17:02 AM.
Official Mashrooi inspection history
Dates and completion percentages are factual source observations. The latest available official photographs are shown above.
- 2024-09-030%Inspection 6548179402 official photo records
- 2025-03-068.48%Inspection 7324994545 official photo records
- 2025-07-1430.46%Inspection 7941142895 official photo records
- 2026-06-2996.92%Inspection 94787973513 official photo records
- 2026-07-1497.48%Inspection 9526570767 official photo records