PROJECT PASSPORT
Wadi Villas By Arista
Official project no. 2967 · Wadi Al Safa 3
OFFICIAL COMPLETION
48.65%
Latest Mashrooi observation
OFFICIAL STATUS
Active
AREA
Wadi Al Safa 3
LAST EVIDENCE
7/29/2026
OFFICIAL RECORD
Project details
- Registered developer
- PBG REAL ESTATE DEVELOPMENT L.L.C
- Master developer
- MEYDAN GROUP (L.L.C)
- Area
- Wadi Al Safa 3
- Registration date
- 2024-03-01
- Listed completion date
- 2026-12-31
- Map coordinate
- View this project on the map →
OFFICIAL EVIDENCE
Official inspection photos
Mashrooi photos shown in their supplied resolution.
Source provenance
Official public registry retrieved on 7/28/2026, 3:30:52 PM · Artifact ffee59d637b1… · 3039 dataset rows. Official Mashrooi details retrieved on 7/29/2026, 9:14:34 AM.
Official Mashrooi inspection history
Dates and completion percentages are factual source observations. The latest available official photographs are shown above.
- 2024-02-190%Inspection 5899974614 official photo records
- 2024-09-250.26%Inspection 6702413104 official photo records
- 2025-01-073.8%Inspection 7109710535 official photo records
- 2025-03-2810.29%Inspection 7455226326 official photo records
- 2025-07-3120.61%Inspection 8012245749 official photo records
- 2026-01-0532.18%Inspection 8689746827 official photo records
- 2026-05-0548.65%Inspection 92730978610 official photo records