PROJECT PASSPORT
Shoaq
Official project no. 3630 · Palm Deira
OFFICIAL COMPLETION
5.57%
Latest Mashrooi observation
OFFICIAL STATUS
Active
AREA
Palm Deira
LAST EVIDENCE
7/29/2026
OFFICIAL RECORD
Project details
- Registered developer
- AVENEW REAL ESTATE DEVELOPMENT L.L.C
- Master developer
- NAKHEEL .(P J S C)
- Area
- Palm Deira
- Registration date
- 2025-09-30
- Listed completion date
- 2027-10-30
- Map coordinate
- View this project on the map →
OFFICIAL EVIDENCE
Official inspection photos
Mashrooi photos shown in their supplied resolution.
Source provenance
Official public registry retrieved on 7/28/2026, 3:30:52 PM · Artifact ffee59d637b1… · 3039 dataset rows. Official Mashrooi details retrieved on 7/29/2026, 2:36:14 PM.
Official Mashrooi inspection history
Dates and completion percentages are factual source observations. The latest available official photographs are shown above.
- 2025-04-100%Inspection 7428258342 official photo records
- 2025-10-240.31%Inspection 8373740742 official photo records
- 2026-02-192.35%Inspection 8960240164 official photo records
- 2026-05-015.57%Inspection 9289840305 official photo records