PROJECT PASSPORT
Rukan 3
Official project no. 2217 · Wadi Al Safa 7
OFFICIAL COMPLETION
100%
Latest Mashrooi observation
OFFICIAL STATUS
Finished
AREA
Wadi Al Safa 7
LAST EVIDENCE
7/28/2026
OFFICIAL RECORD
Project details
- Registered developer
- CONTINENTAL INVESTMENTS LMD L.L.C
- Master developer
- DUBAI LAND RESIDENCES (L.L.C)
- Area
- Wadi Al Safa 7
- Registration date
- 2020-07-10
- Listed completion date
- 2022-12-31
- Map coordinate
- View this project on the map →
OFFICIAL EVIDENCE
Official inspection photos
Mashrooi photos shown in their supplied resolution.
Source provenance
Official public registry retrieved on 7/28/2026, 3:30:52 PM · Artifact ffee59d637b1… · 3039 dataset rows. Official Mashrooi details retrieved on 7/28/2026, 7:28:14 PM.
Official Mashrooi inspection history
Dates and completion percentages are factual source observations. The latest available official photographs are shown above.
- 2021-01-1810.13%Inspection 34351816410 official photo records
- 2021-06-1630.08%Inspection 36475749410 official photo records
- 2021-12-2657.94%Inspection 39308312912 official photo records
- 2022-08-0176.51%Inspection 43220037012 official photo records
- 2023-01-1392.36%Inspection 47521862810 official photo records
- 2025-01-1498.08%Inspection 7355362538 official photo records
- 2026-07-13100%Inspection 95259917113 official photo records