OFFICIAL COMPLETION
63.61%
Latest Mashrooi observation
OFFICIAL STATUS
Active
AREA
Island 2
LAST EVIDENCE
7/29/2026
OFFICIAL RECORD
Project details
- Registered developer
- DHRE 2 BTS L.L.C
- Master developer
- JUMEIRA BAY L.L.C
- Area
- Island 2
- Registration date
- 2023-02-07
- Listed completion date
- 2027-03-27
- Map coordinate
- View this project on the map →
OFFICIAL EVIDENCE
Latest official inspection photos
Mashrooi photos shown in their supplied resolution.
Source provenance
Official public registry retrieved on 7/28/2026, 3:30:52 PM · Artifact ffee59d637b1… · 3039 dataset rows. Official Mashrooi details retrieved on 7/29/2026, 6:42:44 AM.
Official Mashrooi inspection history
Dates and completion percentages are factual source observations. The latest available official photographs are shown above.
- 2022-11-100%Inspection 4575849353 official photo records
- 2023-09-040.06%Inspection 5355563035 official photo records
- 2024-04-011.36%Inspection 6216617341 official photo record
- 2024-09-208.6%Inspection 6806258004 official photo records
- 2025-01-1614.71%Inspection 7131956505 official photo records
- 2025-04-3019.38%Inspection 7596162414 official photo records
- 2025-07-2523.19%Inspection 79873516711 official photo records
- 2025-10-1536.45%Inspection 8320855718 official photo records
- 2026-01-1543.91%Inspection 87957286210 official photo records
- 2026-04-1553.47%Inspection 9193838529 official photo records
- 2026-07-0963.61%Inspection 95108859810 official photo records