Bling Avenue 1
Official project no. 3582 · Madinat Al Mataar
OFFICIAL COMPLETION
68.27%
Latest Mashrooi observation
OFFICIAL STATUS
Active
AREA
Madinat Al Mataar
LAST EVIDENCE
7/29/2026
OFFICIAL RECORD
Project details
- Registered developer
- Bling Development DWC LLC
- Master developer
- DUBAI AVIATION CITY CORPORATION
- Area
- Madinat Al Mataar
- Registration date
- 2024-10-28
- Listed completion date
- 2026-07-28
- Map coordinate
- View this project on the map →
OFFICIAL EVIDENCE
Latest official inspection photos
Mashrooi photos shown in their supplied resolution.
Source provenance
Official public registry retrieved on 7/28/2026, 3:30:52 PM · Artifact ffee59d637b1… · 3039 dataset rows. Official Mashrooi details retrieved on 7/29/2026, 2:06:33 PM.
Official Mashrooi inspection history
Dates and completion percentages are factual source observations. The latest available official photographs are shown above.
- 2025-02-2718.04%Inspection 7331960845 official photo records
- 2025-07-1736.79%Inspection 8045738766 official photo records
- 2025-11-2647.47%Inspection 8527697408 official photo records
- 2026-06-1668.27%Inspection 94297847210 official photo records