PROJECT PASSPORT
Nad Al Sheba Gardens Phase 7
Official project no. 3446 · Nad Al Shiba First
ActiveNAS ESTATES L.L.C
OFFICIAL COMPLETION
2.72%
Latest Mashrooi observation
OFFICIAL STATUS
Active
AREA
Nad Al Shiba First
LAST EVIDENCE
7/29/2026
OFFICIAL RECORD
Project details
- Registered developer
- NAS ESTATES L.L.C
- Master developer
- SHAMAL ESTATES L.L.C
- Area
- Nad Al Shiba First
- Registration date
- 2025-01-28
- Listed completion date
- 2028-02-15
- Map coordinate
- View this project on the map →
OFFICIAL EVIDENCE
Latest official inspection photos
Mashrooi photos shown in their supplied resolution.
Source provenance
Official public registry retrieved on 7/28/2026, 3:30:52 PM · Artifact ffee59d637b1… · 3039 dataset rows. Official Mashrooi details retrieved on 7/29/2026, 12:38:58 PM.
Official Mashrooi inspection history
Dates and completion percentages are factual source observations. The latest available official photographs are shown above.
- 2024-12-090%Inspection 6932058682 official photo records
- 2025-06-100%Inspection 7933455484 official photo records
- 2025-10-070.09%Inspection 8269931033 official photo records
- 2026-02-041.07%Inspection 8886843775 official photo records
- 2026-05-122.72%Inspection 9304656665 official photo records