PROJECT PASSPORT
Reportage Village 1
Official project no. 2784 · Wadi Al Safa 7
OFFICIAL COMPLETION
20.71%
Latest Mashrooi observation
OFFICIAL STATUS
Active
AREA
Wadi Al Safa 7
LAST EVIDENCE
7/29/2026
OFFICIAL RECORD
Project details
- Registered developer
- REPORTAGE PRIME PROPERTIES L.L.C
- Master developer
- DUBAI PROPERTIES(L.L.C)
- Area
- Wadi Al Safa 7
- Registration date
- 2023-12-31
- Listed completion date
- 2027-12-31
- Map coordinate
- View this project on the map →
OFFICIAL EVIDENCE
Latest official inspection photos
Mashrooi photos shown in their supplied resolution.
Source provenance
Official public registry retrieved on 7/28/2026, 3:30:52 PM · Artifact ffee59d637b1… · 3039 dataset rows. Official Mashrooi details retrieved on 7/29/2026, 8:02:20 AM.
Official Mashrooi inspection history
Dates and completion percentages are factual source observations. The latest available official photographs are shown above.
- 2025-04-112.05%Inspection 7510147506 official photo records
- 2025-11-1111.12%Inspection 84483013112 official photo records
- 2026-02-1018.08%Inspection 8935953209 official photo records
- 2026-05-0520.71%Inspection 92860526214 official photo records