OFFICIAL COMPLETION
28.58%
Latest Mashrooi observation
OFFICIAL STATUS
Active
AREA
Jumeirah Second
LAST EVIDENCE
7/29/2026
OFFICIAL RECORD
Project details
- Registered developer
- P M R DEVELOPMENT L.L.C
- Master developer
- MERAAS ESTATES (L.L.C)
- Area
- Jumeirah Second
- Registration date
- 2024-01-20
- Listed completion date
- 2025-12-25
- Map coordinate
- View this project on the map →
OFFICIAL EVIDENCE
Latest official inspection photos
Mashrooi photos shown in their supplied resolution.
Source provenance
Official public registry retrieved on 7/28/2026, 3:30:52 PM · Artifact ffee59d637b1… · 3039 dataset rows. Official Mashrooi details retrieved on 7/29/2026, 8:00:24 AM.
Official Mashrooi inspection history
Dates and completion percentages are factual source observations. The latest available official photographs are shown above.
- 2023-09-210%Inspection 5414462793 official photo records
- 2024-05-212.7%Inspection 6229123264 official photo records
- 2025-01-226.64%Inspection 7183725613 official photo records
- 2025-05-158.65%Inspection 7636638204 official photo records
- 2025-07-2811.99%Inspection 7992327234 official photo records
- 2025-12-1120.76%Inspection 8590075196 official photo records
- 2026-03-2524.3%Inspection 9105920246 official photo records
- 2026-06-0828.58%Inspection 9395159108 official photo records