PROJECT PASSPORT
Skyhills Iii By Hre
Official project no. 3058 · Al Barsha South Fourth
OFFICIAL COMPLETION
67.3%
Latest Mashrooi observation
OFFICIAL STATUS
Active
AREA
Al Barsha South Fourth
LAST EVIDENCE
7/29/2026
OFFICIAL RECORD
Project details
- Registered developer
- HRE REAL ESTATE DEVELOPMENT L.L.C
- Master developer
- JUMEIRAH VILLAGE L.L.C
- Area
- Al Barsha South Fourth
- Registration date
- 2024-06-01
- Listed completion date
- 2026-06-01
- Map coordinate
- View this project on the map →
OFFICIAL EVIDENCE
Latest official inspection photos
Mashrooi photos shown in their supplied resolution.
Source provenance
Official public registry retrieved on 7/28/2026, 3:30:52 PM · Artifact ffee59d637b1… · 3039 dataset rows. Official Mashrooi details retrieved on 7/29/2026, 9:33:55 AM.
Official Mashrooi inspection history
Dates and completion percentages are factual source observations. The latest available official photographs are shown above.
- 2024-07-0420.32%Inspection 6439215923 official photo records
- 2025-03-2423.89%Inspection 7470384316 official photo records
- 2025-07-2628.1%Inspection 8011945718 official photo records
- 2025-11-0448.59%Inspection 8439956997 official photo records
- 2026-02-1258.49%Inspection 89428590412 official photo records
- 2026-05-0767.3%Inspection 93085345614 official photo records