PROJECT PASSPORT
Nad Al Sheba Gardens Phase 4
Official project no. 2915 · Nad Al Shiba First
ActiveNAS ESTATES L.L.C
OFFICIAL COMPLETION
57.04%
Latest Mashrooi observation
OFFICIAL STATUS
Active
AREA
Nad Al Shiba First
LAST EVIDENCE
7/29/2026
OFFICIAL RECORD
Project details
- Registered developer
- NAS ESTATES L.L.C
- Master developer
- SHAMAL ESTATES L.L.C
- Area
- Nad Al Shiba First
- Registration date
- 2024-05-01
- Listed completion date
- —
- Map coordinate
- View this project on the map →
OFFICIAL EVIDENCE
Latest official inspection photos
Mashrooi photos shown in their supplied resolution.
Source provenance
Official public registry retrieved on 7/28/2026, 3:30:52 PM · Artifact ffee59d637b1… · 3039 dataset rows. Official Mashrooi details retrieved on 7/29/2026, 8:59:33 AM.
Official Mashrooi inspection history
Dates and completion percentages are factual source observations. The latest available official photographs are shown above.
- 2024-02-120%Inspection 5882674153 official photo records
- 2025-03-031%Inspection 7394632376 official photo records
- 2025-06-105.56%Inspection 7822974896 official photo records
- 2025-09-1717.1%Inspection 8180085168 official photo records
- 2026-01-0725.75%Inspection 87301719919 official photo records
- 2026-04-2839.24%Inspection 9244933316 official photo records
- 2026-07-1657.04%Inspection 95318089912 official photo records