PROJECT PASSPORT
Athlon By Al Dar 1
Official project no. 3143 · Wadi Al Safa 5
ActiveAURORA SPV 3 L.L.C
OFFICIAL COMPLETION
18.22%
Latest Mashrooi observation
OFFICIAL STATUS
Active
AREA
Wadi Al Safa 5
LAST EVIDENCE
7/29/2026
OFFICIAL RECORD
Project details
- Registered developer
- AURORA SPV 3 L.L.C
- Master developer
- DUBAI PROPERTIES(L.L.C)
- Area
- Wadi Al Safa 5
- Registration date
- 2024-07-16
- Listed completion date
- 2028-05-31
- Map coordinate
- View this project on the map →
OFFICIAL EVIDENCE
Latest official inspection photos
Mashrooi photos shown in their supplied resolution.
Source provenance
Official public registry retrieved on 7/28/2026, 3:30:52 PM · Artifact ffee59d637b1… · 3039 dataset rows. Official Mashrooi details retrieved on 7/29/2026, 10:00:33 AM.
Official Mashrooi inspection history
Dates and completion percentages are factual source observations. The latest available official photographs are shown above.
- 2024-06-190%Inspection 6278105072 official photo records
- 2025-01-100.3%Inspection 7138399273 official photo records
- 2025-06-261.52%Inspection 7931939765 official photo records
- 2025-12-118.32%Inspection 8606318578 official photo records
- 2026-04-1313.16%Inspection 9195948387 official photo records
- 2026-07-2318.22%Inspection 9560739039 official photo records