PROJECT PASSPORT
Damac Hills - Gems Estates 1
Official project no. 2456 · Al Hebiah Third
OFFICIAL COMPLETION
42.35%
Latest Mashrooi observation
OFFICIAL STATUS
Active
AREA
Al Hebiah Third
LAST EVIDENCE
7/29/2026
OFFICIAL RECORD
Project details
- Registered developer
- DAMAC CRESCENT PROPERTIES
- Master developer
- DAMAC CRESCENT PROPERTIES
- Area
- Al Hebiah Third
- Registration date
- 2022-12-15
- Listed completion date
- 2024-09-15
- Map coordinate
- View this project on the map →
OFFICIAL EVIDENCE
Latest official inspection photos
Mashrooi photos shown in their supplied resolution.
Source provenance
Official public registry retrieved on 7/28/2026, 3:30:52 PM · Artifact ffee59d637b1… · 3039 dataset rows. Official Mashrooi details retrieved on 7/29/2026, 6:29:29 AM.
Official Mashrooi inspection history
Dates and completion percentages are factual source observations. The latest available official photographs are shown above.
- 2022-09-150%Inspection 4403939243 official photo records
- 2023-03-200.72%Inspection 4956214243 official photo records
- 2023-08-105.53%Inspection 5312558015 official photo records
- 2023-12-059.52%Inspection 5690508525 official photo records
- 2024-07-0521.07%Inspection 6471592496 official photo records
- 2025-01-2125.41%Inspection 7186868303 official photo records
- 2025-05-1341.94%Inspection 7732649266 official photo records
- 2025-10-2050.85%Inspection 8341836505 official photo records
- 2026-03-2342.35%Inspection 9218133919 official photo records