OFFICIAL COMPLETION
77.91%
Latest Mashrooi observation
OFFICIAL STATUS
Active
AREA
Al Khairan First
LAST EVIDENCE
7/29/2026
OFFICIAL RECORD
Project details
- Registered developer
- DUBAI CREEK HARBOUR L.L.C
- Master developer
- DUBAI CREEK HARBOUR L.L.C
- Area
- Al Khairan First
- Registration date
- 2024-05-09
- Listed completion date
- —
- Map coordinate
- View this project on the map →
OFFICIAL EVIDENCE
Official inspection photos
Mashrooi photos shown in their supplied resolution.
Source provenance
Official public registry retrieved on 7/28/2026, 3:30:52 PM · Artifact ffee59d637b1… · 3039 dataset rows. Official Mashrooi details retrieved on 7/29/2026, 8:46:24 AM.
Official Mashrooi inspection history
Dates and completion percentages are factual source observations. The latest available official photographs are shown above.
- 2023-12-140%Inspection 5690461722 official photo records
- 2024-11-225.87%Inspection 6468763204 official photo records
- 2025-03-1712.93%Inspection 7411101276 official photo records
- 2025-06-2520.22%Inspection 7847825946 official photo records
- 2025-09-3033.01%Inspection 8248767316 official photo records
- 2025-12-3050.21%Inspection 86733216511 official photo records
- 2026-03-2363.55%Inspection 9100073839 official photo records
- 2026-06-2477.91%Inspection 9448976377 official photo records