PROJECT PASSPORT
The Grandala
Official project no. 3046 · Al Satwa
OFFICIAL COMPLETION
62.79%
Latest Mashrooi observation
OFFICIAL STATUS
Active
AREA
Al Satwa
LAST EVIDENCE
7/29/2026
OFFICIAL RECORD
Project details
- Registered developer
- PALLADIUM PRIME REAL ESTATE DEVELOPMENT L.L.C
- Master developer
- MERAAS ESTATES (L.L.C)
- Area
- Al Satwa
- Registration date
- 2024-06-01
- Listed completion date
- 2026-01-31
- Map coordinate
- View this project on the map →
OFFICIAL EVIDENCE
Latest official inspection photos
Mashrooi photos shown in their supplied resolution.
Source provenance
Official public registry retrieved on 7/28/2026, 3:30:52 PM · Artifact ffee59d637b1… · 3039 dataset rows. Official Mashrooi details retrieved on 7/29/2026, 9:33:07 AM.
Official Mashrooi inspection history
Dates and completion percentages are factual source observations. The latest available official photographs are shown above.
- 2024-05-090%Inspection 6130986803 official photo records
- 2025-06-1915.25%Inspection 7879841335 official photo records
- 2025-09-2320.36%Inspection 8195481416 official photo records
- 2026-01-0739.59%Inspection 8742692626 official photo records
- 2026-05-0562.79%Inspection 9285503307 official photo records