PROJECT PASSPORT
La Tilia At Villanova Phase 2
Official project no. 3456 · Wadi Al Safa 5
OFFICIAL COMPLETION
5.35%
Latest Mashrooi observation
OFFICIAL STATUS
Active
AREA
Wadi Al Safa 5
LAST EVIDENCE
7/29/2026
OFFICIAL RECORD
Project details
- Registered developer
- NORTH DUBAILAND PROJECTS L.L.C
- Master developer
- DUBAI PROPERTIES(L.L.C)
- Area
- Wadi Al Safa 5
- Registration date
- 2025-01-21
- Listed completion date
- 2028-08-21
- Map coordinate
- View this project on the map →
OFFICIAL EVIDENCE
Latest official inspection photos
Mashrooi photos shown in their supplied resolution.
Source provenance
Official public registry retrieved on 7/28/2026, 3:30:52 PM · Artifact ffee59d637b1… · 3039 dataset rows. Official Mashrooi details retrieved on 7/29/2026, 1:04:04 PM.
Official Mashrooi inspection history
Dates and completion percentages are factual source observations. The latest available official photographs are shown above.
- 2024-12-180%Inspection 6975722112 official photo records
- 2025-06-260.14%Inspection 7960928954 official photo records
- 2025-09-080.64%Inspection 8153897233 official photo records
- 2025-12-221.07%Inspection 8625270803 official photo records
- 2026-03-241.46%Inspection 9104244374 official photo records
- 2026-06-295.35%Inspection 9468107745 official photo records