PROJECT PASSPORT
The Valley - Elora
Official project no. 2511 · Al Yufrah 1
FinishedEMAAR DEVELOPMENT P.J.S.C.
OFFICIAL COMPLETION
100%
Latest Mashrooi observation
OFFICIAL STATUS
Finished
AREA
Al Yufrah 1
LAST EVIDENCE
7/29/2026
OFFICIAL RECORD
Project details
- Registered developer
- EMAAR DEVELOPMENT P.J.S.C.
- Master developer
- EMAAR DEVELOPMENT P.J.S.C.
- Area
- Al Yufrah 1
- Registration date
- 2023-03-27
- Listed completion date
- 2026-09-30
- Map coordinate
- View this project on the map →
OFFICIAL EVIDENCE
Latest official inspection photos
Mashrooi photos shown in their supplied resolution.
Source provenance
Official public registry retrieved on 7/28/2026, 3:30:52 PM · Artifact ffee59d637b1… · 3039 dataset rows. Official Mashrooi details retrieved on 7/29/2026, 6:42:56 AM.
Official Mashrooi inspection history
Dates and completion percentages are factual source observations. The latest available official photographs are shown above.
- 2022-11-160%Inspection 4587572232 official photo records
- 2023-06-010.87%Inspection 5125183633 official photo records
- 2023-09-211.34%Inspection 5424195423 official photo records
- 2024-03-226.16%Inspection 6066941695 official photo records
- 2024-10-1741.75%Inspection 6776288016 official photo records
- 2025-02-1464.4%Inspection 7290538297 official photo records
- 2025-06-2083.6%Inspection 7835380517 official photo records
- 2025-09-1188.96%Inspection 8196681067 official photo records
- 2025-12-3197.93%Inspection 8687246808 official photo records
- 2026-03-10100%Inspection 90652056819 official photo records