OFFICIAL COMPLETION
64.2%
Latest Mashrooi observation
OFFICIAL STATUS
Active
AREA
Al Khairan First
LAST EVIDENCE
7/29/2026
OFFICIAL RECORD
Project details
- Registered developer
- DUBAI CREEK HARBOUR L.L.C
- Master developer
- DUBAI CREEK HARBOUR L.L.C
- Area
- Al Khairan First
- Registration date
- 2024-12-03
- Listed completion date
- 2029-01-31
- Map coordinate
- View this project on the map →
OFFICIAL EVIDENCE
Official inspection photos
Mashrooi photos shown in their supplied resolution.
Source provenance
Official public registry retrieved on 7/28/2026, 3:30:52 PM · Artifact ffee59d637b1… · 3039 dataset rows. Official Mashrooi details retrieved on 7/29/2026, 10:32:28 AM.
Official Mashrooi inspection history
Dates and completion percentages are factual source observations. The latest available official photographs are shown above.
- 2024-08-020%Inspection 6440554832 official photo records
- 2025-05-239.9%Inspection 8176474495 official photo records
- 2025-10-2124.27%Inspection 8353253127 official photo records
- 2025-12-0431.1%Inspection 8589352586 official photo records
- 2026-03-1751.65%Inspection 9128346267 official photo records
- 2026-06-2564.2%Inspection 9449803198 official photo records