PROJECT PASSPORT
The Valley - Farm Gardens 2
Official project no. 2949 · Al Yufrah 1
OFFICIAL COMPLETION
59.08%
Latest Mashrooi observation
OFFICIAL STATUS
Active
AREA
Al Yufrah 1
LAST EVIDENCE
7/29/2026
OFFICIAL RECORD
Project details
- Registered developer
- EMAAR DEVELOPMENT P.J.S.C.
- Master developer
- EMAAR DEVELOPMENT P.J.S.C.
- Area
- Al Yufrah 1
- Registration date
- 2024-06-27
- Listed completion date
- —
- Map coordinate
- View this project on the map →
OFFICIAL EVIDENCE
Official inspection photos
Mashrooi photos shown in their supplied resolution.
Source provenance
Official public registry retrieved on 7/28/2026, 3:30:52 PM · Artifact ffee59d637b1… · 3039 dataset rows. Official Mashrooi details retrieved on 7/29/2026, 9:03:01 AM.
Official Mashrooi inspection history
Dates and completion percentages are factual source observations. The latest available official photographs are shown above.
- 2024-01-290%Inspection 5839529084 official photo records
- 2024-10-224.62%Inspection 6977549533 official photo records
- 2025-04-298.24%Inspection 7680466626 official photo records
- 2025-07-2420.43%Inspection 7987069258 official photo records
- 2025-09-2924.3%Inspection 8231965198 official photo records
- 2025-12-3035.9%Inspection 8687221969 official photo records
- 2026-03-3150.38%Inspection 9144676166 official photo records
- 2026-07-2059.08%Inspection 95630487110 official photo records