PROJECT PASSPORT
Repose Residence
Official project no. 4012 · Jabal Ali First
OFFICIAL COMPLETION
23.51%
Latest Mashrooi observation
OFFICIAL STATUS
Active
AREA
Jabal Ali First
LAST EVIDENCE
7/29/2026
OFFICIAL RECORD
Project details
- Registered developer
- SAION REAL ESTATE DEVELOPMENT L.L.C
- Master developer
- ALFURJAN ( L.L.C )
- Area
- Jabal Ali First
- Registration date
- 2025-08-01
- Listed completion date
- 2027-03-31
- Map coordinate
- View this project on the map →
OFFICIAL EVIDENCE
Latest official inspection photos
Mashrooi photos shown in their supplied resolution.
Source provenance
Official public registry retrieved on 7/28/2026, 3:30:52 PM · Artifact ffee59d637b1… · 3039 dataset rows. Official Mashrooi details retrieved on 7/29/2026, 4:40:33 PM.
Official Mashrooi inspection history
Dates and completion percentages are factual source observations. The latest available official photographs are shown above.
- 2025-07-310%Inspection 7975275532 official photo records
- 2026-02-2515.94%Inspection 9005581037 official photo records
- 2026-06-2523.51%Inspection 9458295915 official photo records