PROJECT PASSPORT
Alaya
Official project no. 2322 · Al Hebiah Fourth
OFFICIAL COMPLETION
88.01%
Latest Mashrooi observation
OFFICIAL STATUS
Active
AREA
Al Hebiah Fourth
LAST EVIDENCE
7/29/2026
OFFICIAL RECORD
Project details
- Registered developer
- MAJID AL FUTTAIM TILAL AL GHAF PHASE A L.L.C
- Master developer
- MAJID AL FUTTAIM EMIRATI COMMUNITIES OPERATION L.L.C
- Area
- Al Hebiah Fourth
- Registration date
- 2022-03-31
- Listed completion date
- 2026-07-20
- Map coordinate
- View this project on the map →
OFFICIAL EVIDENCE
Latest official inspection photos
Mashrooi photos shown in their supplied resolution.
Source provenance
Official public registry retrieved on 7/28/2026, 3:30:52 PM · Artifact ffee59d637b1… · 3039 dataset rows. Official Mashrooi details retrieved on 7/29/2026, 4:56:51 AM.
Official Mashrooi inspection history
Dates and completion percentages are factual source observations. The latest available official photographs are shown above.
- 2022-06-070.35%Inspection 4225585525 official photo records
- 2022-11-010.48%Inspection 4522049925 official photo records
- 2023-03-070.67%Inspection 4910428735 official photo records
- 2023-07-170.79%Inspection 5240239435 official photo records
- 2024-05-012.28%Inspection 6152312943 official photo records
- 2024-07-248.11%Inspection 6438771503 official photo records
- 2024-11-1522.81%Inspection 6911554296 official photo records
- 2025-03-0536.88%Inspection 7352653586 official photo records
- 2025-05-0146.49%Inspection 7685140387 official photo records
- 2025-08-2061.05%Inspection 8180084758 official photo records
- 2025-10-2163.14%Inspection 8349485049 official photo records
- 2026-01-2679.11%Inspection 88398434920 official photo records
- 2026-03-1785.03%Inspection 90803376615 official photo records
- 2026-06-1088.01%Inspection 9409788797 official photo records