OFFICIAL COMPLETION
100%
Latest Mashrooi observation
OFFICIAL STATUS
Finished
AREA
Palm Deira
LAST EVIDENCE
7/29/2026
OFFICIAL RECORD
Project details
- Registered developer
- METAC PROPERTIES L.L.C
- Master developer
- NAKHEEL .(P J S C)
- Area
- Palm Deira
- Registration date
- 2023-09-15
- Listed completion date
- 2025-12-26
- Map coordinate
- View this project on the map →
OFFICIAL EVIDENCE
Latest official inspection photos
Mashrooi photos shown in their supplied resolution.
Source provenance
Official public registry retrieved on 7/28/2026, 3:30:52 PM · Artifact ffee59d637b1… · 3039 dataset rows. Official Mashrooi details retrieved on 7/29/2026, 7:59:16 AM.
Official Mashrooi inspection history
Dates and completion percentages are factual source observations. The latest available official photographs are shown above.
- 2023-09-140%Inspection 5380669364 official photo records
- 2024-04-011.09%Inspection 6043084095 official photo records
- 2024-07-017.04%Inspection 6466103953 official photo records
- 2024-10-2215.56%Inspection 6799154365 official photo records
- 2024-12-1021.54%Inspection 7040998453 official photo records
- 2025-04-2850.05%Inspection 75888405311 official photo records
- 2025-07-2457.43%Inspection 7983465937 official photo records
- 2025-12-0894.73%Inspection 85647864811 official photo records
- 2026-03-1196.42%Inspection 90638863410 official photo records
- 2026-04-14100%Inspection 92378839721 official photo records