OFFICIAL COMPLETION
73.77%
Latest Mashrooi observation
OFFICIAL STATUS
Active
AREA
Business Bay
LAST EVIDENCE
7/29/2026
OFFICIAL RECORD
Project details
- Registered developer
- PAX INVESTMENT L.L.C
- Master developer
- BUSINESS BAY (L.L.C)
- Area
- Business Bay
- Registration date
- 2023-03-15
- Listed completion date
- 2025-07-30
- Map coordinate
- View this project on the map →
OFFICIAL EVIDENCE
Latest official inspection photos
Mashrooi photos shown in their supplied resolution.
Source provenance
Official public registry retrieved on 7/28/2026, 3:30:52 PM · Artifact ffee59d637b1… · 3039 dataset rows. Official Mashrooi details retrieved on 7/29/2026, 6:29:39 AM.
Official Mashrooi inspection history
Dates and completion percentages are factual source observations. The latest available official photographs are shown above.
- 2022-09-150%Inspection 4410955212 official photo records
- 2023-04-110.1%Inspection 891101864 official photo records
- 2023-08-093.99%Inspection 5301806835 official photo records
- 2024-03-147.34%Inspection 6034793445 official photo records
- 2024-07-0514.98%Inspection 6482058392 official photo records
- 2025-01-2118.83%Inspection 7202767825 official photo records
- 2025-04-1029.94%Inspection 7480994146 official photo records
- 2025-08-0447.82%Inspection 8011448457 official photo records
- 2025-12-1159.03%Inspection 8578255687 official photo records
- 2026-04-0873.77%Inspection 9217684779 official photo records