Dalmore Tower
Official project no. 3622 · Wadi Al Safa 5
OFFICIAL COMPLETION
86.78%
Latest Mashrooi observation
OFFICIAL STATUS
Active
AREA
Wadi Al Safa 5
LAST EVIDENCE
7/29/2026
OFFICIAL RECORD
Project details
- Registered developer
- DALMORE REAL ESTATE DEVELOPMENT L.L.C
- Master developer
- DUBAI LAND RESIDENCES (L.L.C)
- Area
- Wadi Al Safa 5
- Registration date
- 2024-10-24
- Listed completion date
- 2026-04-23
- Map coordinate
- View this project on the map →
OFFICIAL EVIDENCE
Official inspection photos
Mashrooi photos shown in their supplied resolution.
Source provenance
Official public registry retrieved on 7/28/2026, 3:30:52 PM · Artifact ffee59d637b1… · 3039 dataset rows. Official Mashrooi details retrieved on 7/29/2026, 2:35:36 PM.
Official Mashrooi inspection history
Dates and completion percentages are factual source observations. The latest available official photographs are shown above.
- 2025-04-1420.62%Inspection 7519123938 official photo records
- 2025-06-1831.19%Inspection 7834284296 official photo records
- 2025-10-2859.09%Inspection 8395904408 official photo records
- 2026-05-1986.78%Inspection 9343457119 official photo records