PROJECT PASSPORT
Park Gate 2
Official project no. 3641 · Hadaeq Sheikh Mohammed Bin Rashid
ActiveDUBAI HILLS ESTATE L.L.C
OFFICIAL COMPLETION
55.15%
Latest Mashrooi observation
OFFICIAL STATUS
Active
AREA
Hadaeq Sheikh Mohammed Bin Rashid
LAST EVIDENCE
7/29/2026
OFFICIAL RECORD
Project details
- Registered developer
- DUBAI HILLS ESTATE L.L.C
- Master developer
- DUBAI HILLS ESTATE L.L.C
- Area
- Hadaeq Sheikh Mohammed Bin Rashid
- Registration date
- 2025-06-17
- Listed completion date
- 2027-02-28
- Map coordinate
- View this project on the map →
OFFICIAL EVIDENCE
Official inspection photos
Mashrooi photos shown in their supplied resolution.
Source provenance
Official public registry retrieved on 7/28/2026, 3:30:52 PM · Artifact ffee59d637b1… · 3039 dataset rows. Official Mashrooi details retrieved on 7/29/2026, 2:37:27 PM.
Official Mashrooi inspection history
Dates and completion percentages are factual source observations. The latest available official photographs are shown above.
- 2025-04-020%Inspection 7396242212 official photo records
- 2025-07-302.17%Inspection 8002328074 official photo records
- 2025-11-0516.93%Inspection 84246383110 official photo records
- 2026-02-1947.69%Inspection 89859919618 official photo records
- 2026-06-0855.15%Inspection 9380912476 official photo records