PROJECT PASSPORT
Palm Beach Towers - 2
Official project no. 2429 · Palm Jumeirah
OFFICIAL COMPLETION
79.56%
Latest Mashrooi observation
OFFICIAL STATUS
Active
AREA
Palm Jumeirah
LAST EVIDENCE
7/29/2026
OFFICIAL RECORD
Project details
- Registered developer
- THE PALM - JUMEIRAH CO. (L.L.C)
- Master developer
- NAKHEEL .(P J S C)
- Area
- Palm Jumeirah
- Registration date
- 2022-12-01
- Listed completion date
- 2026-12-31
- Map coordinate
- View this project on the map →
OFFICIAL EVIDENCE
Latest official inspection photos
Mashrooi photos shown in their supplied resolution.
Source provenance
Official public registry retrieved on 7/28/2026, 3:30:52 PM · Artifact ffee59d637b1… · 3039 dataset rows. Official Mashrooi details retrieved on 7/29/2026, 6:28:30 AM.
Official Mashrooi inspection history
Dates and completion percentages are factual source observations. The latest available official photographs are shown above.
- 2022-06-2032.82%Inspection 43017097810 official photo records
- 2022-11-1532.82%Inspection 4585451774 official photo records
- 2023-04-1232.82%Inspection 896067665 official photo records
- 2023-08-1532.88%Inspection 5325931768 official photo records
- 2023-11-2233.95%Inspection 5640922267 official photo records
- 2024-01-2536.41%Inspection 5872320153 official photo records
- 2024-05-2837.7%Inspection 6226431266 official photo records
- 2024-09-2547.69%Inspection 6775860656 official photo records
- 2025-01-2358.28%Inspection 71867837511 official photo records
- 2025-04-3064.05%Inspection 75884547812 official photo records
- 2025-10-2369.03%Inspection 8397285338 official photo records
- 2026-02-1177.15%Inspection 8948473848 official photo records
- 2026-05-2179.56%Inspection 9411659338 official photo records