The Waterside Villas By Ellington
Official project no. 2716 · Wadi Al Safa 3
OFFICIAL COMPLETION
31.74%
Latest Mashrooi observation
OFFICIAL STATUS
Active
AREA
Wadi Al Safa 3
LAST EVIDENCE
7/29/2026
OFFICIAL RECORD
Project details
- Registered developer
- ELLINGTON PROPERTIES DEVELOPMENT L.L.C
- Master developer
- MEYDAN GROUP (L.L.C)
- Area
- Wadi Al Safa 3
- Registration date
- 2023-06-21
- Listed completion date
- 2026-06-30
- Map coordinate
- View this project on the map →
OFFICIAL EVIDENCE
Latest official inspection photos
Mashrooi photos shown in their supplied resolution.
Source provenance
Official public registry retrieved on 7/28/2026, 3:30:52 PM · Artifact ffee59d637b1… · 3039 dataset rows. Official Mashrooi details retrieved on 7/29/2026, 7:49:52 AM.
Official Mashrooi inspection history
Dates and completion percentages are factual source observations. The latest available official photographs are shown above.
- 2023-07-100%Inspection 5213560734 official photo records
- 2024-07-020.05%Inspection 6390979082 official photo records
- 2025-06-042.49%Inspection 7839196785 official photo records
- 2025-10-166.97%Inspection 8330489166 official photo records
- 2026-02-0217.19%Inspection 8884473577 official photo records
- 2026-06-0931.74%Inspection 9395795468 official photo records